8 March 2004 � Alstom has set a benchmark by completing a generator rotor rewind in 22 days, against the industry standard of 42 days. This project was completed for the 660 MW Majuba power plant, ...
Mechanical Dynamics & Analysis (MD&A) recently completed generator field rewind with a rotor slot dovetail repair on a customer’s GE® 650,000 KVA generator field. The work scope was performed at the ...